Wind farm investors face growing losses from “curtailments,” as turbine installations outstrip the capacity of local transmission systems to accommodate the new power.

The issue is a “growing pain” of wind technology, Judah Rose, Senior Vice President, ICF International in McLean, VA, said. Curtailment has become an increasing problem since 2008 as wind capacity nationwide increases from almost nothing 10 years ago to more than 42,000 megawatts now. “It’s occurring even in RTOs (regional transmission organizations) with advanced pricing and management systems,” Rose said. Keep reading →


Last week I wrote about the planning reforms contained in Order 1000, the Federal Energy Regulatory Commission’s landmark rule on transmission planning and cost allocation. Today’s blog looks at Order 1000’s cost allocation implications – basically, how to figure out who pays for new transmission development.

Clements’ previous blog, as well as this one, both appeared originally on the NRDC staff blog, Switchboard. Keep reading →