Aitken


A biomass generation plant serving a giant Department of Energy installation has been delivered under the largest Energy Savings Performance Contract to date.

The 20 MW biomass power facility will provide roughly 30% of the 310 square mile Savannah River Site‘s power needs once it becomes fully operational in 2012. During six weeks of performance tests the biomass facility produced more than 3 million kilowatt hours of power. Keep reading →